WORLDWIDE ELECTRIC STOCK CO., LTD. >> Metal-Clad Removable AC Metal Enclosed Switch Equipment

Metal-Clad Removable AC Metal Enclosed Switch Equipment

Metal-Clad Removable AC Metal Enclosed Switch Equipment
Price: US $ 5000/Piece
Trade Terms: FOB,CFR,EXW
Min Order: 1/Piece
Pay Type: L/C,T/T

Product Specifications

Prod Model: KYN28-12
Markets: North America,South America,Eastern Europe,Southeast Asia,Africa,Oceania,Mid East,Eastern Asia,Western Europe
Material: Stainless Steel
Type: High-voltage
Structure: Three-column Disconnector
Installation: Indoor High-voltage
Operation: Electric
Grounding: Double Ground
Series: Four
Run: Turn the Horizontal
Switching Mode: Double-Throw Type
Certification: CE

Product Description

KYN28-12 (Z) indoor drawer style metal-clad switchgear
User's manual
I. General 
KYN28-12 (Z) indoor drawer style metal-clad switchgear is a set of power distribution device of rated voltage 3 to 12KV three-phase AC 50Hz of single bus bar and single bus bar segmental system. It is applicable to power transmission of the power plant, power receiving and distribution of the electric system and the substation of the industrial enterprises to fulfill the aims of control, protection and inspection.
This switchgear can meet the requirements of GB3906, IEC298 and so on, which has the "five-prevention" functions of preventing the error operation of the circuit breaker, preventing the push-and -pull of the hand drawer on-load, preventing from switching the grounding switch with power on, preventing the power transmission of the grounding switch in grounding position and the power spacer to prevent error entry. This switchgear is truly a power distribution device with super performance, which can adopt VD4 vacuum circuit breaker from ABB Company or VS1 vacuum circuit breaker at home.
 
II. Use condition
Environment temperature:  -15ºC to +40ºC
Relative humidity: daily average ≤95%     monthly average≤90%
Height above sea level: ≤1000m
Earthquake magnitude ≤8   
No fire, explosion danger, serious pollution, or chemical erosion occasion.
 
IIIMain characteristics
The structure of the cabinet is bolt by aluminum zinc alloy board after the process of CNC machine tool and multi bending technology;
All the operation can be done after the cabinet door is closed;
High protection degree, protect the intruder of sundries and pests;
Simple and effective "five-prevention" lock function, protect error operation;
Can adopt VS1 and CD4 vacuum circuit breaker;
Easy replacement of the circuit breaker and free exchange of the drawers;
The cabinet can be installed by the wall, maintenance in the front, which reduces the floor space;
Large space of the cable room can connect many cables;
The relay room and the cable room can respectively add a heater to avoid freezing or erosion.
 
IVMajor technical parameters                                                                                Major technical parameters of vacuum switchgear
No.NameUnitData 
1Rated VoltageKV3,6,10
2Rated CurrentA630,1000,1250,1600,
2000,2500,3150
3Rated FrequencyHz50
4Rated short-time tolerant voltagekA20, 25, 31.5, 40
5Rated peak tolerant voltagekA50, 63, 80, 100
6Rated power frequency toleranvoltageInter-polar /polar to groundkV42/1min
Inter-fracturekV48/1min
7Rated lightening shock tolerant voltageInter-polar /polar to groundkV75
Inter-fracturekV85
8Rated lasting time of short-circuits4
9Protection degree Shell IP4X, interval room IP2X
Major parameters of vacuum breakers
No.NameUnitData 
1Rated voltagekV3, 6, 10
2Rated frequencyHz50
3Rated currentA630, 1250,1600,2000,2500,3150
4Rated open circuit current when short circuitkA20,25,31.5,40
54s hot stable currentkA20,25,31.5,40
6Rated dynamic stable current(peak value)kA50,63, 80,100
7Rated power frequency toleranvoltageInter-polar /polar to groundkV42/1min
Inter-fracturekV48/1min
8Rated lightening shock tolerant voltageInter-polar /polar to groundkV75
Inter-fracturekV85
9Rated lasting time of short-circuits4
 
V. Instruction of the structure
The cabinet is composed of the fixed cabinet body and the drawable part (the drawers). The cabinet shell and the interval boards are all bolt with aluminum zinc alloy boards. The protection degree of the cabinet shell can reach up IP4X, and IP2X of each interval room.
The cabinet has the functions of overhead inlet and outlet, cable inlet and outlet and left-right contact. Arrange the scheme cabinets according to usage to compose a power distribution device which can fulfill the designed function. 
The installation and the commission of the switchgear can be done in the front. The cabinet can stand by the wall to save the floor space and lower the investment.
1. The cabinet body
The body and the interval boards of the cabinet are bolt by aluminum zinc alloy board after the process of CNC machine tool and multi bending technology, so that the cabinets assembled can guarantee the unity of the structure and the dimension. The aluminum zinc alloy board has the functions of corrosion resistance and oxidation resistance, and has the higher mechanical robustness than the ordinary steel board. The cabinet is divided to drawer room, bus bar room, cable room and relay instrument room by the interval boards with each unit grounding separately. The doors of the cabinet are all handled with the technology process of electrostatic gunning to make the surfaces have the advantages of anti-impaction, corrosion resistance, and beauty and so on. 
2. The drawer
The drawers can be classed to circuit breaker drawer, voltage transformer drawer, metering drawer, separation drawer and station used variety drawer according to different usage. The drawers with the same usage can exchange each other. The drawers have test/separating and working positions inside the cabinet, each position with an interlock unit to ensure the drawers can't move freely in the above two positions. 
3. Circuit breaker drawer room
A special channel has been installed in the isolation room to provide the drawer to move. When the circuit breaker is moving between the test position and the working position, the separating valve automatically opens or closes to ensure that the operating staff can't get in touch with the charged body. The drawers can be operated in the condition that the cabinet door is closed. The position where the drawer is inside the cabinet can be seen through the monitoring window, and any of the labels on the drawer can also be seen. All these guarantee the safety of the operating and the maintenance staff.
4. Bus bar room
The main bus bar is lead from one cabinet to another cabinet and it is firmed by branch little bus bar and electrostatic contact box. It is fixed by bus bar bushing when it goes through the side wall of the neighbor cabinet.
5. Cable room
Adequate cable room not only can connect many cables, but also can install current transformer, grounding switch and lightning arrester and so no.
6. Instrument room
The internal plate and the panel of the relay room can install control and protection elementsthe meter, the displaying instrument and the monitoring indicator and so on secondary elements.
7. Interlock unit
The cabinet has a reliable interlock unit in accordance with the "five-prevention" requirement, which actually guarantee the safety of the operating staff and the device:
a. An attention button and an alternation switch KK are installed on the room door to avoid the error switch on/off of the circuit breaker;
b. The circuit breaker can not move after switching on in working position to avoid the error pull or close of the separating contact;
c. The grounding switch can switch on only the drawer of the circuit breaker exits the cabinet and the drawer can not enter the cabinet at the same time (the grounding switch can match a voltage monitoring unit). The grounding switch can not switch on when the drawer is in the cabinet, thus fulfill the preventions of closing the grounding switch with power and closing the circuit breaker before the grounding switch is open;
d. The bottom door and the back door can not open after the circuit breaker entering the cabinet to avoid the error entry with power interval;
e. The drawer of the circuit breaker can switch off manually only without switching on when it actually is in test or working position and has no control voltage;
f. The secondary plug is locked and can not be pulled out when the drawer is in working position.
8. Grounding position
In the cable room, TMY40*4 grounding bus bar has been set independently. This bus bar can go through every neighbor cabinet and can get a good connection with the cabinet body to ensure the safety of the operating staff and the cabinet body.
9. Pressure releasing unit
Pressure releasing units have been set at the upside of the drawer room, bus bar room and the cable room. When the circuit breaker or the bus bar arises inner electric arc, with the appearance of the electric arc, the air pressure in the cabinet grows and the pressure releasing unit will automatically open to release the pressure and air when the pressure reaches up to a certain value to ensure the safety of the operation staff and the cabinet body.
 
VI. Structure diagrams and overall dimension (see the attached diagrams) 
 
VII. The installation of the switchgear (see the attached diagrams) 
1. Basis style
The construction of the basis of the switchgear shall conform to the relative specification of "technology specifications of electric power construction and inspection".
The installation basis of the switchgear needs to water the concrete twice. The first time to water the concrete is for the installation components of the switchgear that is for the angle steel, square steel or the installation basis of the channel steel. The second time is to water the additional layer of the concrete, usually 60mm in thickness. The height of the concrete shall be 1 to 3mm lower than the surface of the component when water the additional layer of the concrete.
See the attached diagrams for the basic structure frame.
The installation quality shall be ensured when install the basic structure frame. The technology standard of the installation of the structure frame is 1m2 with 1mm tolerance.
2. The installation of the switchgear
See the attached diagrams for the installation basis and installation dimension of the switchgear.
When the cabinet body is unistrand, the passage before the cabinet is 2.5m for the best and 3m when biserial.
Transport the switchgear to the certain place according to the need of the project and the indication of the diagram. If arrange a long line of cabinets (more than 10 sets), the arrangement work shall be started from the middle.
Use special transportation vehicles such as cranes or forklifts. Rollers and crowbars are prohibited.
Take out the drawer of the circuit breaker inside the cabinet; put it in another place for good care.
Loosen the switch to move away the cable cover.
Move away the cover from the control slot on the left side of the cabinet. The cover of the control slot on the right front side shall be moved away in the same way.
Disboard the lifting board and the fastener.
Install the cabinets in sequence on the above basis. The installation plainness of the switchgear shall not exceed 2mm both in horizon position and in vertical position.
When finish the switchgear assembly, it can be connected with the basic structure frame by ground crews or welded by electro-welding.
3. The installation of the bus bar
The bus bars in the switchgear are all segmental square bus bars. Only the quantity and the specification of the bus bar are different when different current has been chosen, thus the following installation processes have to be followed:
Clean the bus bar with a soft clean and dry cloth; check if the isolation bushing is damaged; coat the connecting parts with some conducting cream or neutral Vaseline.
Install the bus bar one cabinet after one cabinet; connect the bus bar section with the corresponding branch small bus bar and insert proper pads when bolting; fasten it with screws.
4. Grounding unit of the switchgear
Connect the grounding bus bar of each cabinet on the preinstalled connecting board;
Connect all the grounding lead inside the cabinet;
 Connect the basic structure with the grounding terminals;
Connect the grounding line of the grounding knife switch with the main grounding bus bar of the distribution plate.
 
VIII. Primary circuit scheme (see the attached diagram)
 
IX. Example of the scheme application (see the attached diagram)
 
X. Order notice:
The following materials should be provided by the users when ordering:
1. The scheme no. of the main wiring, diagram of single line system, range diagram and arrangement plan;
2. Wiring diagram of the secondary loop and the diagram of the arrangement of the terminals;
3. The type, specification and quantity of the electric elements of the switchgear;
4. The specification and the material of the main bus bar and the branch bus bar;
5. Quantity of accessories or spare parts;
6. Special requirements need to be negotiated with the factory;
7. Whereas the standard, material, technology requirement and installation dimension in this manual will be developed with the time pass by, our company keeps the rights for adjusting the maintenance information. 
Attached:
structure diagram and overall dimension:
 
 
 
 
A bus bar room      B hand buggy room of the circuit breaker
C cable room        D instrument room of the relay
1.1 pressure releasing device               1.2 control little slot
1. The shell                             11. Grounding main bus bar
2. Branch bus bar                        12. Assembly isolating board
3. Bus bar bushing                       13. The isolating board
4. The main bus bar                      14. The secondary plug
5. Static contact device                   15. Hand buggy of the circuit breaker
6. Static contact box                     16. The heater
7. Current transformer                    17. Withdrawable horizontal isolating board
8. The ground switch                    18. Operating mechanism of the grounding switch
9. The cable                            19. The bottom board
10. Lightning arrester
 
 
 



Worldwide Electric Group Co., Ltd (called Worldwide for short) is a technology joint-stock enterprise specialized in R&D, manufacture and operation. Our products are energy-saving & controlling equipments of electromotor, energy saving & automation of electrical power system, high & low switch cabinet and turn-key system, numerical control machines etc. They are widely used in building materials, chemical industry, metallurgy, mining, machinery, automobiles, municipal, power, household appliances and so on.

Since established in 2000, Worldwide abides by the management conception of "making famous brand product, offering famous brand service, being famous brand enterprise", aiming to provide superior products and high-quality service to customers all over the world. We insist on scientific progress and innovation, and 17 types of our products won the national patents. Through 10 years of development, Worldwide is a famous leading group in China's electrical control and optoelectronics field which has 3 subsidiary companies, over 600 employees, nearly $80 million annual sales and the company scale rank No. 1 in the trade.

In the next few years, Worldwide will improve operation management mechanism to reach the annual sales of $150 million to realize our ideal of "Rooted in wide China, and aspiring for the whole world".

Send your message to this supplier

  • WORLDWIDE ELECTRIC STOCK CO., LTD.

Other Products From This Manufacturer